Noida Airport Metro: Is There a Metro to Jewar Yet? A Status Board of Every Aqua Line Extension

10 November 2026 · Rise Propworld Team

Short answer: not yet. Five Noida Metro projects get mixed up in headlines. Here is what each one is, what was approved, what is only proposed, and where reports disagree.

Noida Airport Metro: Is There a Metro to Jewar Yet? A Status Board of Every Aqua Line Extension

Short answer: not yet.

As of 10 November 2026, none of the sources we opened describes a metro line that runs to the Noida International Airport at Jewar. What exists is a set of Aqua Line extensions at different stages, plus two airport links that are proposals. The confusion is understandable, because reports quote different lengths, costs and station lists for what sounds like the same project.

If you are searching for Noida airport metro, this status board sorts the five projects people mix up. Each line says what a named source reported, with its date, and where reports disagree we show both numbers instead of picking one.

Noida airport metro: the status board

ProjectReported length and stationsReported statusSource
Existing Aqua Line, Sector 51 to Depot29.7 km, 21 stationsOperatingMetro Rail News, Wikipedia
Depot to Bodaki (Boraki)2.6 km, 2 stations, ₹416.34 croreApproved by the Centre in July 2025Wikipedia, Metro Rail News
Botanical Garden to Sector 14211.56 km, 8 stations, ₹2,254 croreUnion Cabinet approved on 14 February 2026Metro Rail News
Sector 51 to Knowledge Park V (Greater Noida West)17.435 km, 11 stations in the UP Cabinet DPR of 2024Railway Board NOC reported June 2026, central approval not confirmedMillennium Post, Pulse of Noida
Sector 148 to Noida Airport, and Ballabhgarh to Noida AirportLength not statedProposed onlyWikipedia

1. The line that runs today

The Aqua Line is 29.7 km long with 21 stations, running from Noida Sector 51 to the Depot station, according to Metro Rail News and Wikipedia's Noida Metro page. Fares are listed as ₹10 to ₹50 by Metro Rail News. It does not go to Jewar.

2. Botanical Garden to Sector 142: approved, but on the Noida side

Metro Rail News reported on 19 February 2026 that the Union Cabinet approved this extension on 14 February 2026. It is 11.56 km, elevated, with 8 new stations, an estimated cost of ₹2,254 crore, and a completion target of within four years. It branches from Botanical Garden, which would become an interchange for the Aqua, Blue and Magenta lines.

Swarajya described this corridor in February 2025 as a mass transit link between Delhi and the upcoming airport at Jewar. That is the argument for it. It is not a train to the airport. The route ends at Sector 142 in Noida, not at Jewar.

3. Sector 51 to Knowledge Park V: the Greater Noida West line

This is the one Greater Noida West residents ask us about most. Here is what we found, in order.

  • November 2024. Millennium Post reported the Uttar Pradesh Cabinet approved a 17.435 km extension with 11 stations, at ₹2,991.60 crore, and that the DPR still needed central clearance.
  • April 2026. Metro Rail News carries a headline saying the Centre turned down the Greater Noida metro project and asked for a fresh DPR. We could read only the headline, not the story.
  • June 2026. Pulse of Noida reported a Railway Board NOC. It also said the revised DPR, central approval, funding structure, tender and construction start were all still pending.
  • July 2026. BusinessToday reported a shorter first phase of about 7.5 km with five stations: Sector 61, Sector 70, Sector 122, Sector 123 and Greater Noida Sector 4 near Kisan Chowk. It said the Public Investment Board presentation was the next formal step, not final approval.
  • September 2026. Metro Rail News carries a headline saying the project may get Cabinet approval that month. We could not find a story confirming it did.

So the honest answer on 10 November 2026: we found no confirmed central approval for this line. If you read a headline that says "approved", check whether it means the UP Cabinet in 2024, the Railway Board NOC in 2026, or the Union Cabinet.

Reports also disagree on money. BusinessToday gave a preliminary estimate of about ₹1,000 crore in one piece and ₹1,500 crore in another for the 7.5 km phase, and the 2024 DPR figure was ₹2,991.60 crore for the full length. We are not choosing one.

Planning a home here? Our earlier piece on the Greater Noida West metro stations and pending approval is worth reading next to this one, and our Greater Noida West versus Noida Extension explainer clears up the naming.

Want help judging a Greater Noida West project where "metro nearby" is part of the pitch? Message us on WhatsApp and we will check what has actually been approved on +91 9540400407.

4. The two airport links that are proposals

Wikipedia's Noida Metro page lists a Noida Sector 148 to Noida International Airport link and a Ballabhgarh to Noida Airport link as proposed only, with no length stated. It also lists a Personal Rapid Transit idea from the airport to a Greater Noida amusement park sector, up to 16 km, which is not a metro.

We treat Wikipedia as a summary, not as a primary source, and the page is not consistent about whether the airport is "proposed" or "opened". The airport has opened, which we covered in our report on the June 2026 launch and what it means for prices. The metro links to it are what remain on paper.

5. What about the RRTS?

BusinessToday reported that the Greater Noida West extension is separate from the Regional Rapid Transit System, and that NMRC says it would improve last mile access to the proposed Jewar airport by linking to the RRTS network at interchange points. That is a statement of intent in a news report, not an operating service.

What this means for a buyer

Frequently asked questions

Is there a metro to Noida International Airport?

Not in the sources we opened. The Aqua Line runs from Sector 51 to Depot, and the airport links listed on Wikipedia are proposals. We will update this if an operating line is announced.

Has the Greater Noida West metro been approved?

The Uttar Pradesh Cabinet approved a DPR in November 2024, and a Railway Board NOC was reported in June 2026. We found no confirmed central approval, so check the latest NMRC announcement before relying on it.

Which Aqua Line extension did the Union Cabinet approve?

The Botanical Garden to Sector 142 extension, 11.56 km with 8 stations at ₹2,254 crore, approved on 14 February 2026 per Metro Rail News.

How many stations are planned on the Greater Noida West line?

Eleven stations in the 2024 UP Cabinet DPR, and five stations in the shorter 7.5 km first phase reported by BusinessToday in July 2026.

When will the Greater Noida West metro open?

No confirmed date. BusinessToday reported NMRC estimates about two years of construction after approvals, which means the date depends on approvals that were not confirmed in the sources we opened.

Get the facts on a project's metro claim

We check transit claims against named approvals before we recommend a home. Tell us the project and we will tell you what we find.

Chat on WhatsApp about metro access for your shortlist on +91 9540400407.

Hero image: "Noida Metro7" by Rameshng, licensed CC BY-SA 3.0, via Wikimedia Commons.

Sources: Metro Rail News, "Union Cabinet Approves ₹2,254 Crore Noida Metro Aqua Line Extension" (19 February 2026) and its Noida Metro project page headlines; Millennium Post, "UP Cabinet approves Metro extension to Gr Noida West" (24 November 2024); Pulse of Noida, "Railway Board NOC for Greater Noida West Metro" (19 June 2026); BusinessToday, "Fed up with Noida traffic? This Metro extension could save you time if approved today" (23 July 2026) and "Noida Metro Aqua Line extension: 7.5 km, 5 new stations" (23 July 2026); Swarajya, "Noida Metro to Expand to Connect Jewar Airport" (17 February 2025); Wikipedia, "Noida Metro".